Cost and Time Analysis Using Time Cost Trade Off (TCTO) in order to Catch Up With Execution Time (Case Study: Jakarta Islamic Hospital Pondok Kopi Construction Project)

Nurshela, Thesa and Rozy, Nikko (2026) Cost and Time Analysis Using Time Cost Trade Off (TCTO) in order to Catch Up With Execution Time (Case Study: Jakarta Islamic Hospital Pondok Kopi Construction Project). JTSC (Jurnal Teknik Sipil Cendekia), 7 (2). pp. 1-8. ISSN 2723-3375

[thumbnail of Cost And Time Analysis Using Time Cost Trade Off (TCTO) In Order To Catch Up With Execution Time (Case Study: Jakarta Islamic Hospital Pondok Kopi Construction Project)] Text (Cost And Time Analysis Using Time Cost Trade Off (TCTO) In Order To Catch Up With Execution Time (Case Study: Jakarta Islamic Hospital Pondok Kopi Construction Project))
ARTIKEL JURNAL THESA NURSHELA.pdf
Restricted to Repository staff only until 27 May 2031.

Download (1MB)
Official URL: https://doi.org/10.51988/jtsc.v7i2.522

Abstract

In a construction project, there are three crucial aspects to consider, namely time, cost, and quality. The implementation of the Jakarta Islamic Hospital Pondok Kopi construction project faces several obstacles, especially at the stage of foundation structure and concrete structure work. Based on observations at the location, it is estimated that the completion of the construction of the Jakarta Islamic Hospital Pondok Kopi will be delayed or not in accordance with the planned schedule. There are several options that can be used to speed up project activities, including increasing working hours (overtime), adding manpower, adding or changing tools, adding more effective work methods, and other options. Of the several available alternatives, this study will apply two alternatives, namely increasing working hours (overtime) and increasing labor using the Time Cost Trade Off (TCTO) method. The optimization alternative that has the most optimal or efficient total cost and duration is by adding 5 workers because the project duration becomes faster, even though there is an increase in cost, the addition is more optimal or efficient compared to other alternatives, as indicated by a time efficiency of 51,36% and a cost efficiency of -20,02%. This optimization result can be used as an acceleration option for the project party.

Item Type: Article
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction
Divisions: Fakultas Teknik > Teknik Sipil
Depositing User: Thesa Nurshela
Date Deposited: 25 Jun 2026 07:18
Last Modified: 25 Jun 2026 07:18
URI: https://eprints.ugj.ac.id/id/eprint/3395